Qatar Racing & Equestrian Club, Doha, Qatar

With years of experience of handling thoroughbred horses, the club was the obvious choice as a venue for equestrian events at the 15th Asian Games.
To cover the evenement , news installations and constructions were necessary.
The project was realized by Gregori International :

- Construction of two race courses
- A 1500 seats grand stand
- Stables and a parade ring

Type of construction :

First stage of the contract

- Design and construction of two tracks in only just 10 months
- Design drawings, earthworks, installation of the drainage, irrigation and floodlighting system
- Nursery: 12,000 sq. m. grass nursery
- Dirt racetrack : American style training track (24 000 m˛)
- Parade ring
- Time keeping system
- Photo finish system
- Outside Broadcasting Van
- Mobile video display (screen size: 57 m˛)
- Civil engineering work including construction of an asphalt service road, reservoir, pump room, electrical substations, HV room and parking areas
Second stage of the contract

- Design and build of the Grand stand, technical rooms, dope testing facilitiesin a record time of 12 months (end of works planned for May 2003)
- Design, interior decoration, furnishings
- Kitchen, offices, restaurants
- Jockey rooms, weighing rooms, stewards rooms
- Commentator booths
- Lifts (VIP, man lifts, service lift)
- Fire fighting systems
- M&E works including a variable air volume building management system
- Saddling and dope testing facilities
- Corporate boxes, VIP areas
- Royal suites
 
 